Customer: Prysmian Powerlink Services Limited (U.K.)
Scope Of Supply
CLB ULISSE (8 point mooring system)
Cable Laying Barge
8 sets of 60 ton Single Drum Winch
8 sets of Local Control Console
8 sets of Tension Monitoring System
4 sets of 2x132kW Twin Electrohydraulic
Powerpack
2 sets of Vertical Capstan
1 set of Centralized PLC Remote Control System
1 set of 75kW Electrohydraulic Powerpack
Project Background
Prysmian Group has been awarded by National Grid Corporation of the Philippines for the scope of design, supply, installation, and commissioning of a submarine power cable link to connect Negros and Panay islands in the Philippines.
Negros-Panay connection project, known as CNP-1 (Cebu-Negros-Panay phase 1)
Winch Control Configuration
Manual / Synchronization Mode Selector Switch
1) Synchronisation Mode is to operate Fwd 4 winches (Heave / Pay-out) by one joystick and Aft 4 winches (Heave / Pay-out) by one joystick simultaneously
2) This special function will be designed with PLC (programmable logic controller)