DEME (BELGIUM)
Project Record
Customer: Dredging International (Belgium)
Project Owner: Maritime and Port Authority Singapore (MPA)
Type of Vessel: Work Barge with 4 point constant tension mooring spread
Vessel Name: Sirstam
Scope Of Supply
4 sets of 35 ton Single Drum Constant Tension Winch
4 sets of Local Control Stand
4 sets of 90kW Closed Loop Electro Hydraulic Powerpack
1 set of Centralised PLC Remote Control System
Project Background
The Tuas Terminal Phase 1 project is large in scope, and entails the construction of a new port terminal with 20 deep-water berths having a total capacity of 20 million twenty-foot equivalent units (TEUs) per annum. The Joint Venture will be responsible for the erection of an 8.6-kilometre quay wall and its foundation, the dredging of the fairway and basins, as well as the reclamation of 294 hectares of new land. This major project is expected to complete within six years (by 2020).
To achieve this, more than 80 million cubic metres of reclamation fill will be used comprising dredged materials from the seabed, excavated materials from other land-based projects and sea sand. Laid with a foundation of 222 caissons each weighing about 15,000 tonnes, the quay wall will be fabricated at a temporary yard on site and transported using a newly constructed 20,000-tonne floating dock vessel. One of DEME’s most powerful rock cutter suction dredgers and a trailer suction dredger will also be deployed for the dredging works. The construction activities shall be executed according to strict environmental requirements specified and with continuous environmental monitoring supervision by an independent environmental specialist appointed by MPA.